Thursday 30 August 2012

Hand Dug Caisson Pile

28 numbers of hand dug caisson pile at P11-P17
Date Start : 15 February 2012
Progress : very bad
Target completion date : unknown
Impact : MIP4

Incident 16 August 2012

Kemalangan ke2 melibatkan SBG
Kemalangan berlaku kira-kira jam 12:30 pagi 16 August 2012.
Location : P7-P8
SBG slide down at 6m above ground
Tiada workers cedera
Siasatan masih dijalankan

Kemalangan Pertama: SBG pier Bracket dropped during dismantling at Stn 2
2 workers cedera

Tuesday 28 August 2012


Handing Over for Line Segment Zero (LS zero)

LS zero is from P1 to P8
Scope of works : relocation of 33kv by KCCU
Stiching at P1D1
Special Crossing 42-65-42 Type B for mainline
Special Crossing 42-66-42 Type C for depot access track 1 (north access)
KCCU access date : 31 March 2012
Target completion date : June or Nov 2012????